Consumer guide. No company pays for a ranking.How we make moneyOhio · Illinois · Texas

Concrete footing and sonotube calculator: yards and bags

Last reviewed Reviewed by the Top Concrete Workers editorial team 4 min read 4 sources

Footing and post hole concrete

Pick a shape and enter the size. Results update as you type.

Short answer

For a rectangular footing, multiply length by width by depth in feet and divide by 27 for cubic yards. For a round tube, use pi x radius squared x height. A 10 inch tube 4 feet deep holds about 2.2 cubic feet, or 4 bags of 80 lb mix. Your local building department sets the required depth.

Key facts

  • The 2021 IRC requires exterior footings at least 12 inches below undisturbed ground, and below the local frost line where frost protection applies.[1]
  • The IRC leaves the frost line depth to each jurisdiction, which fills in the minimum footing depth below finish grade in Table R301.2.[2]
  • An 80 lb bag of QUIKRETE Concrete Mix yields about 0.60 cubic feet.[3]

Safety first

This tool estimates concrete volume only. It does not size a footing for a load. Footings that carry a house, an addition, a deck or a porch need a permit in many places and should follow approved plans. Have buried utility lines marked before you dig.

Rectangular footings and pads

Use this for strip (trench) footings under a wall and square pads under a post.

Cubic feet = length (ft) x width (ft) x depth (ft). Convert inches to feet by dividing by 12. Cubic yards = cubic feet / 27.

Examples:

FootingMathCubic feetCubic yards
Strip, 40 ft long, 16 in wide, 8 in deep40 x 1.333 x 0.66735.61.32
Strip, 40 ft long, 12 in wide, 6 in deep40 x 1 x 0.520.00.74
Square pad, 24 x 24 in, 12 in deep2 x 2 x 14.00.15

The 12 by 6 inch strip matches the IRC's smallest allowed concrete footing for a house wall, at least 12 inches wide and 6 inches thick[1]. The 24 inch pad needs 7 bags of 80 lb mix (4.0 / 0.60, rounded up)[3].

Round footings and sonotubes

Cardboard tube forms, often called by the brand name Sonotube, make round piers and post footings. The volume of a cylinder is:

Cubic feet = pi x radius (ft) x radius (ft) x height (ft), with pi about 3.1416. The radius is half the diameter, so a 10 inch tube has a 5 inch radius, or 0.417 feet.

Bags per tube: worked examples at 4 feet deep

Tube diameterCubic feet per foot of depthCubic feet at 4 ftCubic yards80 lb bags60 lb bags40 lb bags
8 in0.3491.400.052345
10 in0.5452.180.081458
12 in0.7853.140.1166711

Bags use QUIKRETE's yields of 0.60, 0.45 and 0.30 cubic feet for 80, 60 and 40 lb bags[3], rounded up, before any waste allowance. For a different depth, multiply the per-foot figure by your depth in feet. A bell-shaped base or a hole wider than the tube holds more, so measure the hole, not just the form.

How to calculate footings for concrete

  1. Pick the shape: box (strip or pad) or cylinder (tube or round hole).
  2. Measure in feet, converting inches by dividing by 12.
  3. Box: length x width x depth. Cylinder: 3.1416 x radius x radius x depth.
  4. Multiply by the number of footings.
  5. Add about 10% for waste[4].
  6. Divide by 27 for cubic yards, or by the bag yield for bags[3], and round up.

How deep should my concrete footing be?

As deep as your local code requires, and the answer depends on where you live:

  • At least 12 inches below undisturbed ground. The 2021 IRC requires this for exterior footings[1].
  • Below the frost line, where frost protection applies. IRC R403.1.4.1 requires foundation walls, piers and other permanent supports to extend below the frost line in Table R301.2, unless protected another approved way, and footings must not bear on frozen soil[1].
  • Your local building department sets the number. The IRC does not print one national frost depth. Each jurisdiction fills in the frost line depth column with the minimum footing depth below finish grade[2]. Call your building department or check its adopted code before you dig.
  • Some small structures are exempt. The IRC exempts frost protection for free-standing light-frame accessory buildings of 600 square feet or less with an eave height of 10 feet or less[1]. Deck footings follow their own section, R507.3[1].

Local codes adopt different editions with amendments, so treat these as model-code rules and confirm locally. For why depth matters in cold climates, see frost heave.

For a simple fence post, QUIKRETE's data sheet suggests a hole about 3 times the post's diameter and one-third of the post's height deep, and says load-bearing uses should follow local building codes[3].

When to call a pro

  • Any footing that supports a house, addition, porch roof or deck, which should follow approved plans or a structural engineer's design.
  • Cracked, settling or heaving footings under an existing structure, which call for a structural engineer, not a patch.
  • Clay soil, fill or a high water table, where the soil may not carry the load the tables assume.
  • Large pours, where a contractor in your area and a ready-mix truck usually beat mixing bags.

More questions

What size footing does my project need?

The calculator gives volume, not design. For a house, the IRC sets minimum footing sizes from tables based on stories, loads and soil, with a floor of 12 inches wide and 6 inches thick [1]. Footings for piers and columns are sized from the load and soil bearing value [1]. For anything that holds up a structure, follow your approved plans or ask a structural engineer.

Do I need to add extra concrete for a tube?

Yes. Holes are rarely perfectly sized and some concrete spills. Family Handyman advises adding 10% to a calculated order [4], and a bag or two spare on a post job is cheap insurance.

Sources

  1. 2021 International Residential Code, Chapter 4 Foundations (Sections R403.1.1, R403.1.4, R403.1.4.1), International Code Council. Accessed 2026-10-15.
  2. 2021 International Residential Code, Chapter 3 Building Planning (Table R301.2, footnote b), International Code Council. Accessed 2026-10-15.
  3. Concrete Mix, Product No. 1101 data sheet (revised October 2022), The QUIKRETE Companies. Accessed 2026-10-15.
  4. How to Estimate a Concrete Order (updated May 12, 2023), Family Handyman. Accessed 2026-10-15.

Top Concrete Workers is an information and referral service run by Strive LeadGen LLC. We may be paid by contractors when we connect a homeowner with one; that never changes what we publish. Found an error? Tell us. We review safety and legal reports within 2 business days and all others within 7 days.

Free quote · Ohio, Illinois, Texas

Get a concrete quote from one local contractor

What do you need?
  • We name the contractor before sharing anything
  • Your details go to one company, never a list
  • Free, no obligation. Stop texts anytime

Ohio, Illinois and Texas. For a wall, slab or structure that is moving fast, or a gas smell, leave the area and call 911 or your gas utility.